Installation and dismantling of pavilions and modules

Martin Bøger Guzek
Co-founder | Chief Business Development Officer

+45 2428 4200

Martin.Guzek@Accera.dk

Accera is a total supplier when pavilions and temporary modules need to be installed, made ready for use, or dismantled again. That is shown not least by the collaboration with Expandia, described on this site as one of the leading module rental companies in the Nordic region.

In autumn 2024 Accera was appointed total supplier for the full delivery of a temporary office-module facility of 2,400 m² at the Technical University of Denmark, DTU Lyngby. Accera was responsible for the solutions and the installation of the 38 modules, which were coordinated, positioned and craned into place within a timeframe of 2½ months. Accera has also been total supplier for the installation of Expandia’s module solution at Søndermarkskolen in Frederiksberg.

Clients have a dedicated project manager on each project and a single point of contact for all the trades involved, both when the facility is put up and when it is taken down.

Services

Accera handles both the installation and the dismantling of pavilions and modules.

The installation services below are documented on the DTU project, where Accera was responsible for the full delivery:

  • Site preparation and technical surveying
  • Excavation and sewer systems
  • Supply of water, electricity and data
  • Site logistics and coordination
  • Electrical and fibre installation
  • Work on ventilation systems
  • Carpentry and fitting
  • Interior installation across trades
  • Project management and stakeholder coordination

On the DTU project the scope also included a temporary foundation with 1,300 tonnes of crushed concrete, a vapour barrier and a layer of heavy timber as the base for the modules, cranage and assembly of 38 modules, roof drainage, outdoor lighting, 550 m² of outdoor concrete paving, 130 metres of plasterboard walls with doors, wireless lighting systems, fibre runs in the ground, filling, sanding, felting and painting, repairs to vinyl floors, and the installation of 42 air-to-air heat pumps.

Dismantling is part of the same service when pavilions and modules are taken down after use.

Who the service is for

The service covers installation and dismantling of pavilions and modules. What the published references document is work for a module rental company and temporary facilities at the end user’s site:

  • Rental companies for flexible and temporary module and pavilion solutions, as in the collaboration with Expandia
  • Temporary office modules, as at DTU Lyngby
  • Temporary facilities during renovation, as at Søndermarkskolen in Frederiksberg

How the installation at DTU Lyngby was carried out

The sequence below is taken from the DTU case and describes that installation project; it is not a general process guarantee for every assignment.

  1. Surveying and site works. Accera carried out the preparatory work so the site was ready for installation. The area was surveyed precisely.
  2. Technical services. Power supply, water solutions and connections, and a sewer extension were completed before the temporary foundation was established.
  3. Temporary foundation. After excavation, the foundation was finished with 1,300 tonnes of crushed concrete, which was compacted and levelled.
  4. Protection and base. A vapour barrier was installed, and a layer of heavy timber was laid to secure the position of the modules on the temporary base.
  5. Cranage and assembly. Accera coordinated, positioned and craned a total of 38 modules.
  6. Technical connections. Once the modules were in place, electricity, ventilation, water and external installations were connected. Fibre was run in the ground and integrated into the modules.
  7. External finish. The modules were assembled so that the exterior appeared as a single unit. Roof drainage, outdoor lighting and 550 m² of outdoor concrete paving were established.
  8. Interior adaptation. The client chose a different room layout, so the interior walls were removed before the new layout was built. 130 metres of plasterboard walls with doors were constructed, wireless lighting was installed for the individual rooms, vinyl floors were repaired, surfaces were filled, sanded, felted and painted, and 42 air-to-air heat pumps were installed.

The project was completed within the 2½-month timeframe, including after the client requested extensive changes to the interior layout along the way.

Case excerpt: Expandia at DTU Lyngby

In autumn 2024 Expandia appointed Accera as total supplier for the full delivery. Accera was responsible for all solutions and for the installation of 2,400 m² of temporary office modules at DTU Lyngby. Within 2½ months Accera staffed the surveying and excavation, fit-out, water, lighting, electrical work and coordination of plant. 38 modules were craned into place, and the facility was connected and fitted out, including after changes to the interior room layout.

«Accera has established itself as a reliable contractor. Expandia Moduler has collaborated with Accera on multiple projects and look forward to future opportunities. We also appreciate having a consistent single point of contact, for this instance we valued Jonas’s professionalism and efficiency in his work.»

— Bjørn Rhyding, Operations manager, Expandia Moduler

Read the full case. Accera has also installed Expandia’s module solution at Søndermarkskolen in Frederiksberg.

Contact

If you would like Accera to assess an assignment involving the installation or dismantling of pavilions and modules, please get in touch. We respond within 48 hours. If the matter is urgent, please call.